Well, it has now been two weeks since the last post and much has happened.  I am including photos from each week so you can see the progress that has been made…

 

work on the roof week 1

 

Roof over classrooms finished and sealed…

Demolition completed up to the front of the building…

Entryway wall being plastered…

 

Hallway being completed with area for stairway to the second floor…

 

Window protection in the last classroom finished…

Almost finished!!!

Thanks to Ian Wilke who came down and helped last week, installing doors, cutting tile for the floor, mixing concrete, and much more.  We hope to have the pictures of the completed classroom for next week!