The work keeps going…

This past week the storage room was finished, the roof tile installed over the second classroom and plastering completed on various walls, not to mention all of the material that the men load into wheelbarrows to take from the street back to the courtyard to use for the work…

 

Storage room ceiling completed…

 

Walls being plastered…

 

One part of the roof ready to pour, the other part with roof tile installed ready for sealer.  More pictures to follow next week!